Roadway SR-836 Dolphin Expressway Interchange Improvements
View Project →

SR-836 Dolphin Expressway Interchange Improvements

Client: FDOT District 6 Value: $14.2M Duration: 18 Mos

Served as lead civil subcontractor for the interchange widening and realignment. Scope included 120,000 CY of earthwork, 22,000 tons of Superpave asphalt, 8,400 LF of storm drainage, and full MOT across six active lanes. Completed 14 days ahead of schedule with zero lost-time incidents.

Roadway NW 27th Avenue Roadway Reconstruction
View Project →

NW 27th Avenue Roadway Reconstruction

Client: Miami-Dade County Value: $8.7M Duration: 14 Mos

Complete roadway reconstruction from NW 79th Street to NW 95th Street including full-depth asphalt removal, limerock base, new Type S-3 structural course and FC-12.5 friction course, ADA-compliant sidewalks, curb and gutter, and storm sewer upgrades.

Site Development Lakewood Estates Subdivision Phase II
View Project →

Lakewood Estates Subdivision — Phase II

Client: Lennar Homes Value: $6.3M Duration: 10 Mos

Turnkey site development for a 180-lot single-family subdivision in western Broward County. Scope included mass excavation (275,000 CY), lake excavation, road construction, water and sewer main installation, storm drainage, and final grading.

Utilities City of Doral NW 87th Avenue Utility Relocation
View Project →

City of Doral — NW 87th Avenue Utility Relocation

Client: City of Doral Value: $4.1M Duration: 8 Mos

Relocated 6,200 LF of 16" water main and 4,800 LF of 12" force main to accommodate the NW 87th Avenue widening project. Work performed in active right-of-way with full MOT, bypass pumping, and coordinated utility shutdowns.

Earthwork Homestead Air Reserve Base Apron & Taxiway Reconstruction
View Project →

Homestead Air Reserve Base — Apron & Taxiway

Client: U.S. Army Corps of Engineers Value: $11.5M Duration: 16 Mos

Earthwork and base construction for the reconstruction of two taxiways and a 120,000 SF aircraft parking apron. Scope included 180,000 CY of excavation, lime rock base, underdrains, storm drainage, and coordination with active military flight operations.

Utilities SW 152nd Street Water Main Extension
View Project →

SW 152nd Street Water Main Extension

Client: Miami-Dade WASD Value: $3.8M Duration: 7 Mos

Installed 9,600 LF of 20" ductile iron water main along SW 152nd Street from US-1 to SW 137th Avenue, including 14 fire hydrants, 22 gate valves, connections to two existing mains, and full road restoration.

$350M+
Total Project Value Delivered
500+
Projects Completed
3.2M+
Cubic Yards of Earth Moved
185+ Miles
of Utilities Installed

What General Contractors & Owners Say

Real feedback from the project executives who trust BC&E with critical path work.

“

BC&E has been our go-to civil sub for the past six years. They show up when they say they will, their prices are competitive, and their work quality is as good as anyone in the market. The SR-836 project was flawless.

“

We contracted BC&E for a utility relocation on a very tight timeline with significant MOT challenges. They pulled it off ahead of schedule and under budget. Christopher and his team are first-class professionals.

“

From preconstruction through final punch list, the BC&E team was organized, communicative, and committed to quality. They self-perform almost everything, which means fewer coordination headaches for us.